All posts by GeneralSteamNavigation

Summer Engineering Update

Summer engineering update

In June a few select volunteers restarted  stripping down work on GSN. Numbers are being strictly limited to begin with to comply with social distancing so it may be a little while before we can welcome new members to our working parties. Thank you to those that have recently sent in their volunteer forms to join the ranks of our working members, we will welcome you to Blunsdon as soon as we are able.

Most of the work focused on getting our container set up which included the installation of the container lights and electrical sockets, at the request of the railway painting the outside green and various other small tasks. Work did progress on the locomotive with the removal of the springs that attach to the centre driving wheels. A preliminary visual inspection suggests they are good condition considering their age.

The removal of the lower piston and cover

Although we await the installation of a permanent electrical feed, we have a temporary connection to our newly installed consumer unit to give us both lighting and a ring main in the container. We have included RCD protected sockets for external tool use, sockets by the desk including USB charging points and sockets for the kindly donated microwave oven, fridge and kettle!

The stripping down also saw the right hand side piston and cover being removed. These have now been put into storage and will their condition will be assessed.

Removing some of the more stubborn bolts

The Society is happy to report that it was able to purchase some new components for the locomotive in the form of a Speedo drive, cut off indicator quadrant & part of the steam turbo generator. The components were from an enthusiast’s collection who offered them to the Society for an incredibly reasonable price.

Work in July was mostly focused around preparing for the boiler lift with some of the more troublesome boiler mounts being removed. The front boiler mounts proved especially resistant to being removed but after some head scratching a plan was devised and carried out that saw the mounts being separated.

 

Front end casing complete with lamps and disks

The main engineering highlight for this issue was the new front end casing which was successfully test fitted in July. The casing was originally built to be a surprise for our members at the cancelled AGM earlier in the year. The casing was built by the team at Leaky Finders who did another fantastic job for us.

Front end view of the casing

The two outside pieces are slightly bigger then they were originally built, we felt it was a sensible decision to make them bigger then we need to allow us trim them down during their final fitting and make a perfect joint to the rest of the casing. For the same reason none of the fitting holes were drilled, this meant we had to use some wooden props to display the pieces on the locomotive. The most complex part of the casing manufacture was the lamp irons which required machining to get the side profiles right before beginning to be bent into their into the final shape.

Boiler lift

CanPacs boiler lift inside Eastleigh works

The “Sponsor an inch or more” campaign that was masterminded by  Graham Muspratt was a huge success with the Society raising just under £2,000. The Society would like to thank Graham and all those who donated to the appeal. Getting the funding in place so quickly has made the planning for the boiler lift far simpler. At the time of publication a date has been agreed for the lift prior to the rearranged AGM although for health and safety reasons the Society will not be publishing the exact date.

With the relaxation of lockdown rules our volunteers have been hard at work preparing for the boiler lift. Our aim is to get all the remaining small boiler tubes cut and removed from the boiler before the day of the lift. The majority of the securing bolts have been removed with the remaining ones being left in for safety reasons. Our volunteers will remove all the final securing bolts the day before the lift.

Preparing the trailing truck for removal

The Society have been debating the possibility of removing both the trailing truck and front bogie whilst the crane is on site for the boiler lift. The agreed plan is to attempt to remove the trailing truck but we’ll leave the front bogie in place.  There are several reasons for this decision with the main factor being the Society is not in a position where we can make the locomotive immobile. The weight of the front end of the locomotive would require us to pack behind the bufferbeam in order to prevent the possibility GSN pivoting on her front drive axle. If GSN had a crank axle in place along side the rear drive wheel would have created a counter weight to balance the locomotive without either the bogie or trailing truck needing to be in place. The safest option we are taking is to remove the trailing truck and leave the bogie in place as this will allow us to push the locomotive back under cover once the lifts have been completed.

All the generous people who donated to the appeal will be entered into a free draw to win a number of prizes, including: a star prize of a Graham Farish N Gauge Merchant Navy Pacific locomotive, a years free membership to the GSNLR society, GSN merchandise and other prizes.

The raffle will be drawn at random at pivotal points during the boiler lift such as: The moment the first inch has been lifted, point of maximum lift, being clear of the chassis and then lowered to its new location. If you have donated and not contacted us to confirm your raffle entry with us please do at the earliest opportunity in order to ensure you don’t miss out.

How you can help us.

With so much engineering progress being made with the restoration of 21c11 / 35011 back to original condition complete with air smoothed casing and chain drive valve gear you can help us in several different ways:

Membership

The General Steam Navigation Locomotive Restoration Society Membership costs £12 for the year click here for more details on how to join us.

Shareholding

The General Steam Navigation C.I.C. offers our supporters the opportunity to purchase shares in the locomotive. To find out more about becoming a shareholder and the levels of benefits click here.

Volunteering

No matter what skills you have we can use your help. Please contact our volunteer liaison officer Mr Andrew Collett at andrew.collett@35011gsn.co.uk.  If you are considering a donation to the project or buying some shares today is the perfect time to do it.

The project is heading into some very exciting times and any financial contributions would be greatly appreciated.

As always thank you for your continued support.

August 2020 Update

Issue 13 of the Packet

 Members of the General Steam Navigation Locomotive Restoration have been receiving their copies of issue 13 of the Packet in the last few days. Full of information and updates on our progress despite Copvid 19! If you are not already a member you are missing out, only £12 per year join online here 35011gsn.co.uk/membership.html we welcome your support.

Proxy Annual General Meeting 2020

The Coronavirus lockdown has caused an unprecedented amount of disruption to our way of life this year and led to us having to cancel our AGM which was scheduled earlier in the spring. The Society had hoped a physical AGM could still take place in 2020, unfortunately in the last few weeks it has become clear that it wouldn’t be possible.

The option that the trustees have decided to take going forward is to hold the Society and CIC (for shareholders) Annual General Meeting by proxy for this year with the expectation of being able to return to normal and hold a physical AGM in March 2021 subject to the relaxation of restrictions to enable us to host a safe event. The proxy AGM will take place on 1st October 2020 and will deal with the Society’s financial year that ended in February 2020 and the CIC financial year that ended in November 2019.

Included with the latest issue of the Packet members will find a booklet which contains all the financial statements for the last financial year, a report from the Society chairman, an agenda for the meeting and a proxy voting form. Please read the booklet carefully and return your proxy voting forms by Friday 25th September. Please note that votes arriving after this date will not be registered, so please send them in at your earliest convenience.

We are living in very uncertain and unusual times but its key that all the legal business of the project is completed correctly, on time and in a transparent manner. This does require a certain amount of flexibility which has been provided to us by the Government.

Twenty Twenty Club

(c) Geoff Dowling
www.flickr.com/photos/geoffsimages/

We are pleased to launch our TWENTY TWENTY CLUB – a great way for you to support the General Steam Navigation Locomotive Restoration Society whilst having a bit of a flutter!

Here’s how it works…

You complete and sign the membership form and Standing Order mandate for £5.00 a month (or £60.00 annually) available for download from our website at https://35011gsn.co.uk/about-us-1/35011-twenty-twenty-club/

Fundraising Coach Trip Postponement

35011 at Southampton (Copyright P Rowlands)

Sadly due to the continuing Covid 19 situation in Lancashire & Yorkshire we have made the tough decision to postpone our joint

fundraising trip with the S&CR. With the current uncertainty and with our member’s welfare in mind we feel this is the best option. The new dates will be 21st-24th May 2021.

We intend to have the same itinerary as planned ( NRM York, North York’s Moors Railway, East Lancs Railway & Bolton & Embsay Railway) but this can’t be confirmed until the railways concerned release their 2021 timetables.

Those of you already booked will be contacted directly. Thank You for your understanding.

 

July Update 2020

Engineering

The Society is pleased to report that we be restarting working parties in July. Numbers will be strictly limited to begin with to comply with social distancing so it may be a little while before we can welcome new members to our working parties. Thank you to those that have recently sent in their volunteer forms to join the ranks of our working members, we will welcome you to Blunsdon as soon as we are able.

In June a few select volunteers restarted  stripping down work on the GSN. Most of the work focused on getting our container set up which included the installation of the container lights and electrical sockets, at the request of the railway painting the outside green and various other small tasks. Work did progress on the locomotive with the removal of the springs that attach to the center drive wheels. A preliminary visual inspection suggests they are good condition considering their age.

The Society also gained a new component in June that was originally fitted to sister Merchant Navy 35023 ‘Holland Afrika Line’. Not many parts of 35023 survived the scrapyard, but luckily after the last fires were dropped from the engines at Nine Elms, souvenirs from the locomotives were recovered, this includes the boiler pressure gauge from 35023, which had recently resurfaced from an old drivers collection. This historic component has now been secured for future use on GSN thanks to the very kind donation of one of our members.

Clothing

You can now look great whilst supporting the restoration of 21c11 / 35011.

The Society is pleased to partner with our friends at Universal Uniform to provide a range of quality 21c11 / 35011 GSN branded clothing items, in a variety of colours, such as:

 

 

 

 

With manufacturing processes having been made fully Covid-19 secure,  all items are made to order and usually despatched within 7-10 working days.

All proceeds from the sale of these clothing items will directly benefit the restoration of 21c11 / 35011.

To visit our dedicated clothing online shop and make your purchases click here

New Dates for Fund raising Trip.

As you are probably aware we have had to reschedule our four day fund raising coach trip to Yorkshire,which subject to getting sufficient numbers will now take place on Friday 16th October.

Profits for the trip will be split between GSN & The Swindon & Cricklade Railway.In my professional capacity as a coach driver I will behind the wheel for the trip so it will be a great way to meet fellow members & raise money at the same time.

We will travel on 3 steam railways,visit the National Railway Museum* at York & generally have a fun weekend. We will be based at the Best Western Guide Post hotel on the outskirts of Bradford for 3 nights on a half board basis.

The program is as follows:

  • Fri 16th Oct. Travel from Blunsdon to Bradford
  • Sat 17th Oct Steam Journey on the Bolton & Embsay Railway followed by a journey from Rawtenstall to Bury on the East Lancs Steam Railway.
  • Sun 18th Oct Steam journey from Pickering to Whitby on the North Yorks Moors Railway.
  • Mon 19th Oct Visit to the NRM York (Subject to NRM reopening after corona virus shut down) before returning to Blunsdon.

Price £299pp. This includes all train fares. There is a £50 single Supplement.

This trip is run in conjunction with Holidays & Cruises in Melksham . To Book please call them on 01225 865725 option 3.

 

How you can help

You can help with the restoration of 21c11 / 35011 back to original condition complete with air smoothed casing and chain driven valve gear in several different ways.

Membership

The General Steam Navigation Locomotive Restoration Society Membership costs £12 for the year click here for more details on how to join us.

Shareholding

The General Steam Navigation C.I.C. offers our supporters the opportunity to purchase shares in the locomotive. To find out more about becoming a shareholder and the levels of benefits click here.

Sponsorship

The Society does have a few components available for sponsorship.

Gauge glass protector (1 available for £80 – 1 already sponsored)

Safety valve castings (1 available for £250 – 2 already sponsored)

Front end cladding and lamp irons are also available for prices

To register an interest in sponsoring any of the components please contact us directly via email, social media on Facebook, Instagram and Twitter or using the contact us form.

As always thank you for your continued support.

 

Bournemouth Belle Anniversary

On this date in 1931 the first Bournemouth Belle ran direct between London Waterloo and Bournemouth Central. The train formed of Pullman stock first ran on Sunday 5 July 1931 and was one of the most famous named trains on the Southern region. The service originally was only scheduled to run during the summer months however due its great success the service was extended to run on all weekends and summer weekdays and in 1936, it became a year-round daily service.

(c) Geoff Dowling
www.flickr.com/photos/geoffsimages/

When the Bournemouth Belle was reintroduced after the Second World War the service saw some major changes. The Southern Railway realised that the potential traffic to Southampton and its cruise ship terminals were too important to miss out on so additional stop at Southampton Central was added. The other major change to the service was the introduction of Oliver Bulleids faster and more powerful Merchant Navy class locomotives including our engine General Steam Navigation, that was a regular locomotive recorded as to haul the service. The size of the train grew considerably after the war with up to twelve Pullman cars weighing almost 500 tons tare weight combined with the requirement of fast acceleration and high top speed the Merchant Navys had a train were they could show off there best qualities. During the final days of steam, in the summer of 1967, the Merchant Navy power gave way to Class 47 diesels which worked the service until its demise on 9 July 1967.

To help one day recreate the sight of General Steam Navigation hauling the Bournemouth Belle you can support our project at www.35011gsn.co.uk/supporting-us.html.

Thank you.

May Update 2020

May Engineering Update

In January and February work progressed on the locomotive at the Blunsdon site. The majority of the effort was focused on preparing the boiler for the lift later in the year. This saw our volunteers removing tubes from the boiler and the various bolts securing the boiler to the frames. The Society is happy to report that all the large boiler tubes have been removed with work now starting on the smaller tubes. It had been hoped the smaller tubes would be all removed before the boiler lift but with workings cancelled until further notice that might not be possible. Whilst our volunteers have removed the majority of the bolts securing the boiler to the frames, several have been left in for safety reasons. Once the boiler lift gets closer the last of these bolts will then be removed and the remainder of the smokebox will also be removed.

Exposed frames after ash pan removal

The stripping down of the locomotive has also seen progress with the ash pans on both sides now removed. Whilst the crane is on site for the boiler lift the Society also plans remove the front bogie and trailing truck. Once these have been removed the bogie, which appears to be in better condition then the trailing truck, will become the main focus of our restoration efforts. It is the aim to restore the trailing truck at the same time although his will depend on the cost effectiveness of the exercise.  It is believed once the Society has delivered a major restored component our credibility will improve and more serious investment will come in.

CAD Boiler support and inside slide bar bracket

During the shut down the Society has also been able to agree a very good value-for-money deal that will see our entire frames, stretchers, bufferbeam and both the front and rear dragboxs drawn up in CAD. Once the boiler has been lifted and the frames stripped back this CAD will then be used to check the frames. The Society has had some CAD produced in the past such as the boiler support which forms the back of the oil bath that contains the chain driven valve gear, mounts the inside slidebar and holds the plunger that transfers the valve motion to the piston valves (see right). The Society will need to check that the locomotive’s frames actually match the CAD and the drawings. Once the frames have been scanned to ensure they are in good condition (and fingers crossed, no cracks or damage) the CAD will then be used to cast any stretchers that will need replacing, along with a new dragbox and the boiler support. The cost of getting the frame CADs done was agreed for a price for £1,500. With funds being very tight after the AGM’s cancellation if anyone would like to contribute towards the cost of the CAD project please do get in touch using the contacts details on our website.

The Society had also hopFront end casinged to unveil some of the front cladding with fitted lamp irons at the AGM in March. The cladding had been produced in order to give the locomotive her face and the start of the outline unique to an original condition Merchant Navy. To create the look some wooden frame extensions were fabricated in order to temporarily fit the new cladding. The cladding had been completed in time for the AGM but with the Covid-19 lock down the Society have been unable to send someone down to collect the finished project. Until the big unveiling the completed cladding will be kept under wraps. The Society would just like to thank Leaky Finders for there hard work constructing the cladding in record time.

The Society was able to acquire a new original electric headlight  for the locomotive.  At this point the Society now has 5 brass lamps and 1 steel one. The Society has also agreed a price for a Smiths speedometer axle box generator and a cut-off indictor plate for the steam reverser which we will be collecting later in the year.

At this moment in time GSN is a dormant creature, waiting for its time to live again & with your help we can do just that. No matter what skills you have we can use your help. Please contact our volunteer liaison officer by email to Andrew Collett or write to him  with your contact details if you fancy getting your hands dirty.

Issue 12 of the Packet

The latest issue of the Packet went out to our members this month and was another bumper issue. The issue features the latest news from the engineering team, the boiler lift appeal,  GSNs backplate build up and much much more.

If you are not yet a member, it’s only £12 per year, you can sign up here. Membership in the Society ensures you’ll be kept up to date with the latest achievements, via our members magazine ‘The Packet’ published three times a year with progress reports on GSN and articles about Merchant Navy’s and the Light Pacifics, access to the locomotive when possible and the ability to get involved with the Society.

With the Covid-19 lockdown in place the Society’s finances are under great strain following the lose revenue generated from our sales stand visiting heritage railway gala events over the year. To help ensure work can continue following the lockdown the Society does ask to consider supporting us if your able to and any support would be gratefully appreciated. You can sign up for membership for only £12 per year here, donate to the Society here or even better join us as a shareholder here.

As always thank you for your continued support.

 

 

March Update 2020 – Boiler Lift Appeal

 Boiler lift “Sponsor an inch or more” and prize draw.

As with all things in life what goes up must come down… and the boiler is no different. It will need to be lifted clear of the chassis, swung away, and then lowered to its new temporary location.

The approximate cost of the crane hire will be £1500 that also equates to approximately the distance in actual up and down travel of 150 inches of the boiler by the time it has been raised to clear the chassis and lowered again.

We are therefore offering supporters the opportunity to sponsor a part of the lift for as little as £10 per inch, of course supporters can also sponsor multiple inches!

How to “Sponsor an inch or more”

To “Sponsor an inch or more” head to our campaign ‘JustGiving’ page here  to complete your sponsorship.

Free prize draw

Every “inch or more” sponsored will be entered into a free draw to win a number of prizes, be drawn at random at pivotal points during the boiler lift, including: model railway locomotives in N and 00 gauges including a star prize of a Graham Farish N Gauge Merchant Navy Pacific locomotive, a year’s free membership of the GSNLR Society, General Stream Navigation merchandise and other prizes.

The more inches sponsored increases your winning chances.

Note: the prize draw is registered with Plymouth City Council in accordance with the Gambling Act 2005 for non-commercial Society’s

Click here to sponsor an inch

AGM Cancelled

We also regret to inform you that we have had to cancel our Society and C.I.C. AGM’s planned for Saturday March 28th. The Swindon and Cricklade Railway have cancelled their Steam Gala and all trains until at least the end of April as a precaution against Covid-19 and your Board has decided that we should follow their very sensible lead.

We hope to be able to arrange the AGM’s for a later date when the current situation resolves itself and we shall announce a new date in a future edition of The Packet and will be writing to all shareholders as well. We apologise for any inconvenience caused to any of you who intended to attend the AGM’s but I am sure you will understand our decision under the circumstances.

Engineering

Our volunteers have also been hard at work removing various components off the locomotive including the rear and middle brake hangers on the right hand side, the remaining parts of the slide bars from both sides, the outside exhaust steam pipes, the reversing screw and the regulator operating bar from inside the boiler. All of the removed components are then assessed, put into storage and if they are a component that is exclusive to the rebuilds they are offered to other Bullied owners group.

Trailing Truck

 Work was not just focused on removing components but also saw our volunteers test fit some of the components the Society had made last year. The main highlight was the trail fitting of all the components for the trailing truck. The spring beams were successfully installed with the hangers. The Society needs to acquire some new springs but was able to use the bogie springs for the test fiting. The axle box cover and dust cover were fitted which gave us the slight of a fully equipped fabricated trailing truck for the first time since the 1960s when GSN had the covers removed at Barry. The Society would once again like to thank all the members who sponsored the various components for the trailing truck.

Boiler

The main focus on the work on the locomotive has been centred around detubing the boiler ready for the boiler lift. As it stands all of the bigger boiler tubes have been removed from the boiler and our volunteers have a start removing the small tubes.

The boiler lift will be part of a big on-site move so getting the boiler prepared and the funds in place beforehand will be key. Once again if you like to help fund the boiler you can “Sponsor an inch or more”  by donating to our campaign ‘JustGiving’ page here  to complete your sponsorship.

As always thank you for your continued support.

AGM CANCELLED

Dear Member / Shareholder,
I regret to inform you that we have had to cancel our Society and C.I.C. AGM’s planned for Saturday March 28th.
The Swindon and Cricklade Railway have cancelled their Steam Gala and all trains until at least the end of April as a precaution against Covid-19 and your Board has decided that we should follow their very sensible lead.
We hope to be able to arrange the AGM’s for a later date when the current situation resolves itself and we shall announce a new date in a future edition of The Packet and will be writing to all shareholders as well.
We apologise for any inconvenience caused to any of you who intended to attend the AGM’s but I am sure you will understand our decision under the circumstances.
Andy Collett, Chairman of GSN C.I.C. and Gerry Leyman, Chairman 35011 GSNLRS.

January 2020 Update

January 2020 Update

Looking back to progress in 2019

Since the move of General Steam Navigation our new home at the Swindon and Cricklade Railway   in April 2019 we have held a number of enjoyable and productive working parties made all the more effective by being at our new permanent base, see also our May 2019 update here.

Working alongside our friends at the Swindon and Cricklade Railway   we have obtained and installed a new 20ft storage container alongside 35011 in the Barn at Blunsdon. This gives us a secure base for our tools, equipment and most importantly storage of many of the components that have been removed from the locomotive to enable the next steps of restoration to take place.

In preparation of lifting the boiler during 2020 we have continued to remove the boiler tubes, with the majority of the large tubes now removed. We also removed the top of the old smokebox, this being both badly corroded and also a of a rebuilt type and therefore not suitable for 35011 when restored to original form, this have given us easier and safer access to the boiler front tubeplate. All the boiler mounting points have been regularly oiled up to enable easier removal of the boiler later this year.

As with a restoration of this kind there are many components that need to be removed from the locomotive as part of the process, some of these items will be restored and reused whilst others being for the engine in her rebuilt form will not be required and where possible a offered to other locomotive owners. All the components so far removed have been catalogued and securely stored. These items have included: slide bars, reverser, cylinder and valve chest covers, glands and packing and brake gear.

We also have continued to work on the production of new items including a wide range of new castings, Klinger valves and bogie and pony truck spring beams and hangers being machined, and trial fitted.  Research and Design work and material sourcing is continuing in earnest for the new centre crank axle and new tyres have been ordered for the wheels for the centre axle.

At our November working party that coincided with Remembrance Sunday, those attending marked the occasion by observing a 2 minutes silence, to remember specifically all those in the Merchant Navy whom lost their lives alongside our service personnel. 35011 was also suitably adorned with the Red Ensign flag of the Merchant Navy.

More details and information about the progress being made on 35011 General Steam Navigation will be in the next issue of our members magazine the Packet due later this month.

If you are not yet a member, it’s only £12 per year, you can sign up here  or even better become a shareholder here.

Upcoming dates in 2020

 

Our next planned working weekends are being held on 25th / 26th January & 29th and February / 1st March.

As always with our working weekends, no experience is necessary just enthusiasm and a willingness to get involved. If you are interested, please contact our chairman at andrew.collett@35011gsn.co.uk for a volunteer form to fill out.

Please note that as well as being a member of us you will also need to be a member of and or join the Swindon & Cricklade Railway.

Also our AGM will be held on the 28th March at the Swindon & Cricklade Railway,  where all members and shareholders are invited to join us. We have a guest speaker from Steam Railway Magazine and it is also a Gala Weekend on the Swindon & Cricklade Railway , so along with seeing the progress that has been made on No.11 there will be plenty going on to make the visit worthwhile.
The formal AGM notice will be in the next issue of the members magazine the Packet.

As always thank you for your continued support.

General Steam Navigation, co-operation between rail and sail

The General Steam Navigation Company was founded in 1821 to run steam ship services from London. Almost 100 years later P&O Navigation bought a controlling interest in the company but it continued to trade under its original name.

It is quite appropriate, therefore, that the General Steam Navigation Locomotive Restoration Society who are rebuilding the Southern Railway Merchant Navy Class Locomotive 35011 named after the General Steam Navigation and the New Medway Steam packet Co (Medway Queen Preservation Society) who have rebuilt a ship that operated under GSN management should work together and support one another’s aims.

The General Steam Navigation Locomotive Restoration Society recently moved their locomotive, Merchant Navy Class 35011, to Blunsdon on the Swindon and Cricklade Railway. There they are working to convert the locomotive back to its 1940s specification; before the class were rebuilt into the more conventional form by British Railways. This includes restoring the iconic air smoothed casing along with Bulleid’s oil bath encased chain driven valve gear. Once complete, General Steam Navigation will be the first engine to be restored to as-built condition within the ranks of preserved Merchant Navy class locomotives.

On the river Medway, the GSNC worked closely with the New Medway Steam Packet Company and Captain J. H. Wills of the GSNC and his wife were on board when PS Medway Queen made her maiden voyage across the Thames Estuary on Friday 18th July 1924. In 1936 GSN acquired the New Medway Company but, again, retained the name for trading purposes.

The Medway Queen Preservation Society have rebuilt their vessel structurally with the aid of HLF funding and are now engaged in fitting out the ship, initially for use as a floating venue for meetings and events. The long term aim is to see the ship sail again under its own power. Medway Queen is berthed in Gillingham, Kent, where a small team of dedicated volunteers are pushing the project forward. Like the locomotive, progress on the ship is governed by the availability of resources – both physical and financial. Although a Kent based organisation, MQPS has worldwide support and has a PR team based, conveniently, in Wiltshire and not far from Blunsdon!

The aims of the two groups’ cooperation will be to support one another in publicity campaigns and appropriate merchandising and marketing initiatives. An early project will be a promotional wagon for 00 model railways. For some years now the Medway Queen has benefitted from income generated by a series of such wagons and it is hoped that a joint project will reach a wider market and generate funds for both teams. Details will be announced when the model goes on sale early in 2020.

For more information on the two societies go to:

www.35011gsn.co.uk  and www.medwayqueen.co.uk

May 2019 Update

Since the last update the Society the project has been incredibly busy with the biggest news being the locomotive has arrived at her new home on the Swindon and Cricklade Railway. The move which took 2 days and involved a crane, 2 low loaders and around 30 volunteers was a complete success with the locomotive arriving at the railway on the 20th April.  The Society would like to thank Reid freight and all the volunteers at Sellindge and Swindon for their help during the move. The Society is also incredibly grateful to all our members who donated towards the costs of the move and raised £1,700 in just under a week. You can still support our efforts to cover the move by donating at https://www.justgiving.com/crowdfunding/35011gsn.

General Steam Navigations move to the Swindon generated quite a bit of main stream media coverage for the project. The stand out achievement was a 3 minute feature on the local BBC 6pm news program ’Points West’. The feature included footage of the locomotive arriving, some old photos, interviews with Andrew Collett one of our trustees and Allan Bott one of the Swindon and Cricklade volunteers. Getting the feature was a great scoop for the project as the program gets an average of 580,000 people tuning in.

Andrew Collett and Allan Bott were also interviewed for BBC Radio Wiltshire’s  Drivetime program. General Steam Navigation also made the front page of the S&CRs local paper the ’Swindon Advertiser’. All this mainstream coverage is a great success for the project and our new hosts as we look to build our volunteer and supporters base in the local area.

The Society held its AGM on the 18th May at Blunsdon station on the Swindon and Cricklade Railway. This year’s event was the first time the Society has been able to hold the AGM with the locomotive present and was the majority of our members’ first time seeing 35011 in person. A full write up will appear in Issue 10 of the Packet out in the next couple of months.

If you are considering getting involved with the restoration of the locomotive joining today is the perfect opportunity to join. Working parties will be starting soon at the Swindon site and will make the next stage of her life and you could be part of that new chapter. For more details please do get in touch with us through our website or various social media platforms.

As always thank you for your continued support.